 Infrastructure Sustainibility: Evaluating Saskatoon's 1912 Interceptor
Click to download the PDF
Mark Andrews, P.Eng., AndrewsInfrastructure, Ottawa, ON
Joseph Uglevich, P.E., OCTC Inc, Stow, Mass
Dale Clancy, P.Eng., Infrastructure Services Dept, Saskatoon, SK
ABSTRACT
The City of Saskatoon’s main Interceptor Sewer comprises some 10 km of sewer
ranging in size from 600 to 2100 mm diameter and was built and commissioned in
stages. The first stage was completed in 1912 to service the original town-site, but
curiously wasn’t commissioned when completed. The Interceptor wasn’t actually
put into service until 1948, after the construction of a comminuter/lift station
facility and an outfall. The final stage of work was completed in 1970 which
included a 4.5 km extension to a new activated sludge sewage treatment plant.
The entire Interceptor was evaluated in 2005 as part of the City’s on-going asset
management program using the WRc approach and based upon findings from
combined CCTV/Sonar inspections, manhole inspections, material testing,
hydrogen sulphide monitoring and ventilation monitoring.
The purpose of this paper is to present an overview of the design and construction
of the 1912 portion of the Interceptor and to show how historical investigations
lead to a better understanding of the sewer’s performance. Historical evidence
was used to determine the materials and products integrated in the Interceptor and
to determine construction techniques.
The staging of the Interceptor construction presented a somewhat unique situation
in terms of assessing its performance and thereby forecasting its long term
maintenance needs. In order to evaluate the current condition of the original 1912
portion of the Interceptor it was necessary to understand something about how it
was designed and constructed. But more importantly, in order to forecast future
maintenance and rehabilitation requirements it was necessary to understand how,
and at what rate, the existing sewer might be deteriorating; and hence the need to
confirm the delay between construction and commissioning.
Historical investigations enabled the engineering team to establish and confirm
critical aspects of the age and life-expectancy of the sewer. This enabled the team
to confidently forecast on-going maintenance needs. It also enabled the team to
better evaluate performance and key characteristics of the sewer, such as joint
condition, structural distress, deviations in longitudinal slope and corrosion
impacts. Recommendations were made regarding maintenance issues and
rehabilitation needs. Findings indicate that the 1912 Interceptor is in relatively
good condition; with on-going maintenance the sewer is expected to provide
useful service for many decades to come.
INTRODUCTION
The 1912 Interceptor comprises 48", 60", 66" and 72" (1200, 1500, 1650 and
1800 mm) diameter pipe as summarized in Table 1. The 1970 sections comprise
72” and 84” (1800 and 2100 mm) diameter pipe. The Spadina Lift Station is an
on-line facility that lifts sewage approximately 15 m from the original outfall
location adjacent to the river, to the upstream end of the new extension.
The assessment of the sewer was carried out in two steps. First a detailed internal
inspection program, utilizing specialized inspection equipment, was undertaken to
document existing field conditions. Second, a detailed review and assessment of
the inspection findings was carried out in order to assign condition grades. It was
during this later stage that historical issues were taken into consideration.
Concrete cores and H2S monitoring results were used to supplement inspection
findings and refine condition assessment conclusions. Condition assessment
rating and conclusions were based on the well-known WRC methodology.
|