Strategies for action are prepared based on the findings from each preceding stage of investigations. Action plans can be developed either for isolated problems or for an entire district or system. One of the most important strategies to be developed is a means to continually re-evaluate findings and adjust priorities as time passes. At an appropriate time new general inspections need to be carried out and hence the maintenance cycle continues.
Andrews Infrastructure has provided the following services:
- Emergency repairs in a failed 1825 mm concrete lined tunnel
- Diversion works to enable de-commissioning of a failed 1350 mm trunk sewer
- Rehabilitation strategy for a 12 km regional trunk sewer
|